How much of the cost of building a house is materials, and how much is labor?

Published

Summary

National data won't give you that split. NAHB's builder survey reports costs by construction stage, and each stage lumps together materials, labor the builder pays directly and subcontractor bills. What the survey does show is which stage a cost lands in, and that turns out to matter when you read a bid, because "site work" in the survey may not mean what it means in a builder's quote.

What NAHB actually measures

The 2024 survey says each category covers all the costs a builder paid for that item: labor paid directly by the general contractor, the cost of hiring subcontractors, and materials, "however they are purchased." A framing number is what it cost to get the house framed, not the lumber bill.

For trade-by-trade unit costs, NAHB points to paid estimating services such as RSMeans and Marshall & Swift/CoreLogic.

Where the dirt work lands

What people often call site workWhere NAHB counts it2024 average
Excavation, foundation, concrete, retaining walls, backfillFoundations$43,002
DrivewayFinal steps$9,635
LandscapingFinal steps$9,269
Building permit feesSite work$7,640
Impact feeSite work$6,367
Water and sewer fees and inspectionsSite work$6,260
Architecture and engineeringSite work$6,480

NAHB's own Site Work total, $32,719 or 7.6% of construction cost, is mostly fees and design, with $5,972 of other items. If a bid has a site-work line for clearing and grading, it isn't measuring the same thing.

The lot sits outside all of it

None of the $428,215 average construction cost includes land. The finished lot, $91,057 including financing, is counted separately in the sales-price breakdown. The full eight-stage percentages are on our cost-to-build page.

Sources

  1. nahb.org/-/media/NAHB/news-and-economics…home-2024-january-2025.pdf